Skip to content Skip to navigation

Project: Upgrade UCL, Library and Presentation Room Desktops (IT Lead: Patrick)

status: 
Completed
important_dates: 

Sept 1, 2018: Project start
Dec 1, 2018: Execution Phase start
Jan 11, 2019: Project End

OPPM Link: 

Taskstart-endstatusAssesmentSept-Oct 2017 

Description: 

(1) Upgrade MDT server and images
(2) Test user profile
(3) Upgrade all desktops

project_date: 
Saturday, December 15, 2018